Mediation ADR
ADR Resolves Planning and
Environmental Court Appeal Dispute

_______________________________________________

DATE:5 September, 2002
LOCATION: A rural part of a South East Queensland
Local Government Area
MEDIATOR: Martin Daubney SC

OUTCOMES: ADR Resolves Planning and Environmental
Court Appeal Dispute
_______________________________________________
Issue A dispute had arisen between adjoining neighbours after an unlawful outdoor recreation use commenced. John Haydon represented one of the neighbours at the mediation.

Subsequently, an application for a material change of use with respect to the outdoor recreation was made to the Local Government and the neighbour became the adverse submitter.

After the Council issued a Development Permit, the Submitters appealed to the Planning and Environment Court. The Council listed the matter for a directions hearing in July, 2002. The matter was set down for hearing in October, 2002 with a timetable for interlocutory steps. No mediation order was included.

Referred to mediation Subsequent to the order being made on the directions hearing the parties agreed to refer the matter to mediation. A Mediation Agreement was signed between the parties and the mediation proceeded on 5 September, 2002. The parties agreed to suspend the timetable under the directions hearing order while the mediation proceeded. The appeal was due to be mentioned at a callover on 27 September, 2002.

After a one day mediation the parties resolve the appeal by amending the conditions. A three day hearing in the Planning and Environment Court was not required. 

Because the parties had suspended timetable disclosure did not take place so substantial costs were saved with respect to advancing the appeal towards a hearing.  All three parties cooperated positively during the mediation process.

Outcome A realignment of the boundaries and a change to easement arrangements including the surrender of one easement and the creation of a new easement were part of the Heads of Agreement signed at the end of the mediation. The Planning Scheme of the Council was respected in the realignment of the boundaries so that the minimum subdivision area was maintained with respect to the two allotments of land. 

As a result of the Heads of Agreement a Consent Judgment was drawn up so that the conditions of the approval were amended by the Court without a contested hearing. Secondly, the Heads of Agreement allowed for the parties to resolve other matters between themselves especially in relation to the realignment of the boundaries and the easement arrangements. The adjustment to the easement is something that the Planning and Environment Court could not order as part of the appeal if there was no agreement. However, because the successors in title to the Grantor and Grantee of the existing easement agreed to its surrender the parties were able to reach a compromise outside the scope of the types of orders that the Planning and Environment Court could have made on a contested hearing of the Submitter Appeal. 

Because of the timing and the speed at which the mediation moved to resolve the dispute the parties saved considerable legal and expert witness costs.

Of Note The negotiation process was assisted by the Solicitors for each of the three parties agreeing to meet on site with a contractor to look at developing options prior to the mediation. There were five options on the table before the mediation commenced.  Because of a legal issue the matter may well have ended up in the Court of Appeal before it was finally resolved. That had been saved in addition to the 3 day hearing in the Planning and Environment Court because of the settlement achieved at the mediation. The parties secured certainty within a reasonably short time frame.